Washington Street Bridge
SFN 1539434
LET-0241-12
Cherry Valley Run
The Following is an up-date on the status of the Washington Street Bridge Replacement Program.
The replacement project was kicked-off December 27, 2013 by applying for funding through the Municipal Bridge Program.
The program is through ODOT.
There were several delays on Environmental studies that were required.
The project will hopefully go out to bid March or April 2022.
We are hoping that construction can start in May 2022.
Estimated overall project cost is $500,000.00