Washington Street Bridge Replacement Program

Ls2 update fb image

Village of Leetonia issued the following announcement on Feb 22.

Washington Street Bridge

SFN  1539434

LET-0241-12

Cherry Valley Run

The Following is an up-date on the status of the Washington Street Bridge Replacement Program.

The replacement project was kicked-off December 27, 2013 by applying for funding through the Municipal Bridge Program.

The program is through ODOT.

There were several delays on Environmental studies that were required.

The project will hopefully go out to bid March or April 2022.

We are hoping that construction can start in May 2022.

Estimated overall project cost is $500,000.00

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS